Roadwork Continues on I-15 in Hesperia to e on Monday Night – Saturday Morning

HESPERIA, CA. (Pain In The Pass) >> The California Department of Transportation (Caltrans) will continue work on a $122 million project to rehabilitate and repave traffic lanes and ramps and upgrade the drainage systems in Hesperia to Victorville in the center divider/right shoulders on Interstate 15 in San Bernardino County. This project will not add a extra lane to the freeway or for a high speed train.

As of the end of June the project is 74% completion and still on track.

THIS WEEK 10-DAY CLOSURE OF THE NORTHBOUND RANCHERO RD. OFF-RAMP from July 23 through August 2. Drivers must take alternate routes. Use Hwy 395 or Main St. Please follow indicated signage posted ahead of closure locations. 

ALSO STARTING THIS WEEK a 10-DAY CLOSURE OF THE NB RANCHERO RD. ON-RAMP from July 30 through August 9. Drivers must take alternate routes. Please follow indicated signage posted ahead of closure locations.

Hours of operation: Monday night – Saturday Morning.

Northbound I-15 from Oak Hill Rd to Bear Valley Rd – 9pm to 7am.**

• Alternating lane closures, possibly bringing lanes down to one at times.

• *All on / off ramps are subject to intermittent closures for crew safety and related roadwork.

• Connector closures may take place: NB/SB I-15 to NB/SB Hwy 395 during operations. Watch for signage.

• NB Ranchero Road, Hwy 395, and Main Street off ramps may be closed:

Southbound I-15 from before Bear Valley Rd to Ranchero Rd – 7pm. – 5am**.

• Alternating lane closures, possibly bringing lanes down to one.

• *All on / off ramps are subject to intermittent closures for crew safety and related roadwork. Main Street and Joshua St may be closed

• Connector closures may take place: NB/SB I-15 to NB/SB US 395 during operations. Watch for signage.

**Times can subject to change and could go longer or start earlier. On and off ramps may be subject to closure. Please use caution and remember to reduce your speed when approaching and driving through the construction zones. Schedules are subject to change due to inclement weather or construction issues.

The project is expected to be complete in Spring 2025.

There are more ways to follow the Pain In The Pass. Join the Traffic Group on Facebook with over 144,000 members. Join the group on MeWe. Like us on the NEW page on Facebook. Follow us on NewsBreak, and also follow us on Instagram, Threads, and X aka Twitter.

loader-image
Cajon Pass
7:21 am, Mar 10, 2026
temperature icon 46°F
broken clouds
Humidity: 88 %
Pressure: 1016 mb
Wind: 16 mph
Wind Gust: 13 mph
Clouds: 57%
Visibility: 10 km
Sunrise: 7:06 am
Sunset: 6:52 pm
  • Temperature
  • Precipitation
  • Rain Chance
  • Wind
  • Humidity
  • Pressure
8:00 am
temperature icon
38°/46°°F 0 mm 0% 8 mph 88% 1016 mb 0 mm/h
11:00 am
temperature icon
50°/57°°F 0 mm 0% 6 mph 77% 1016 mb 0 mm/h
2:00 pm
temperature icon
58°/64°°F 0 mm 0% 6 mph 57% 1015 mb 0 mm/h
5:00 pm
temperature icon
63°/63°°F 0 mm 0% 6 mph 45% 1016 mb 0 mm/h
8:00 pm
temperature icon
53°/53°°F 0 mm 0% 6 mph 72% 1019 mb 0 mm/h
11:00 pm
temperature icon
42°/42°°F 0 mm 0% 3 mph 69% 1021 mb 0 mm/h
2:00 am
temperature icon
51°/51°°F 0 mm 0% 3 mph 57% 1021 mb 0 mm/h
5:00 am
temperature icon
50°/50°°F 0 mm 0% 6 mph 53% 1022 mb 0 mm/h